Hill Country 138 kV line

1,140 structures over 210 miles, inspected in six weeks without an outage.

Client
Regional transmission utility
Year
2025
Role
Visual and thermal inspection

The challenge

The utility needed a full condition survey before summer peak load, with no outages and limited road access.

A country town among fields, from above

The approach

Three crews flew sections in parallel, inspecting each structure with zoom and thermal cameras and tagging every finding to the utility's structure ID.

Farmland around a quiet lake, from above

The result

37 priority findings were sent to line crews within 24 hours, and the full report loaded straight into the utility's asset management system.

Forest and a lake under a clear sky, from above
A town in snowy countryside, from above

Credits

Program manager
Rosa Delgado
Lead pilot
Kurt Bauer
Thermographer
Ann Lee
GIS
Victor Huang

All services

A preview of the Infrastructure template. Linework Inspection is a sample studio and the pictures are stock.About this templateUse this template
Report